New roundabout with underground reinforced concrete tank for collecting 2,000 cubic metres of rainwater Newly constructed cycle path, footpaths and pavements, noise barriers and green areas Overall view of new viability and public lighting

Work direction of urbanisation works in the context of the construction of the new ESSELUNGA super store in Via Porta Nuova in the municipality of Pistoia (PT)

Among the most interesting works of art built on the Esselunga site are a cycle path, 15,000 square metres of urban park with skate park, pedestrian paths and video surveillance system, car parks, underground utilities (gas, sewers, waterworks, public lighting), soundproofing barriers, green spaces with irrigation systems and an underground concrete tank under a new roundabout with a volume of 2,000 cubic metres, all built on site, as well as a 2.5 x 1.5 metre box culvert 250 metres long and a manmade structure with a volume of 2,000 cubic metres, all built on site. a. below a new roundabout with a volume of 2,000 cubic metres, all built on site, as well as a 2.5 x 1.5 metre box culvert 250 metres long and a reinforced concrete structure that acts as a sand trap and retains solid sediments.

CLIENT: ESSELUNGA SpA
DATE: maggio 2017 – settembre 2018
CONTRACT: 5.200.000 €